Works included the formation of ground bearing slabs in-between the brick piers that would later form new stores.
Comast were also tasked with the earthworks to each of the areas, the installation of new service routes into each viaduct, cleaning/preparing of brickwork to be visually beneficial, forming a haul-road between each of the arches which, later, formed part of the walkway/s between the stores and adjacent buildings.
The Contract faced some interesting logistical challenges but our experience ensured that these were overcome. Delivery of each area was completed on programme.
Mace
© Comast Construction 2021. Company Registration: 5557595 | UTR: 3240816814
VAT Registration Number: 745038240